Madison Village

Zoning Fee Schedule

 

A fee, in accordance with the following schedule, shall accompany each application for a

zoning certificate, and shall be deposited to the credit of the General Fund of the Village:

 

 

Description

Amount

1.

Single-family dwelling

$50.00

2.

Accessory building

$20.00 per structure

3.

Two-family dwelling

$70.00

4.

Multiple dwelling

$50.00 (first unit)

$20.00 (per additional unit)

5.

Addition or alteration to existing dwelling.

$25.00

6.

Commercial or industrial permit

(Construction, addition, or alteration)

$0.03/sq. ft. with a $100 minimum and a $500 maximum fee.

 

The fee for the application for a zoning certificate for the use of land not involving structures, including changes in the use of land, shall be $10.00.

 

Additional fees shall be as follows:

 

8.

Copy of the Zoning Code

$10.00 per book

9.

Copy of the Zoning Map

$10.00 each

10.

Fence Permit

$10.00

11.

Pool Permit

$20.00

12.

Sign permit

$10.00

13.

Conditional Use Permit

- PC hearing will be held with notice once in a local paper 15 days prior to the hearing.

- First class mail notice to those within 200’ of the property will be sent 15 days prior to the PC hearing.

 

$100.00 + the current USPS first class mail cost for each person notified.

14.

BZA Application

- BZA hearing will be held with notice once in a local paper 15 days prior to the hearing.

- Certified mail to all adjoining property owners will be sent 15 days prior to the hearing.

 

$100.00 + the current USPS certified mail cost for each person notified.

15.

Rezoning Application

- PC hearing will be held with two local newspaper notices at least 10 days prior to the hearing.

- First class mail notice to those within 200’ of the property will be sent regarding the PC hearing at least 5 days prior to the hearing.

- Council hearing will be held with notice once in a local newspaper 30 days prior to the hearing.

- First class mail notice to those within 200’ of the property will be sent regarding the Council hearing at least 20 days prior to the hearing

 

 

 

$300.00 + twice the current USPS first class mail cost for each person notified.

16.

Subdivision Application

- An application form will be completed by the subdivider.

- The lot fee and engineering deposit will be paid.

- 10 copies of the proposed subdivision will be submitted.

- The submission of said material will be provided to the Zoning

Inspector 20 calendar days prior to the next regular PC meeting.

 

 

$10 per proposed lot  +  an engineering review deposit determined by the Village Engineer.

 